Dear Residents,
Development work in the HaDagan neighborhood is entering its final stage: asphalt paving on the neighborhood's streets.
The schedule is as follows:
*Monday, August 17, 2026*
From approximately 07:00 to 13:00, asphalt paving work will take place on *HaHarish* Street.
From approximately 13:00 to 19:00, asphalt paving work will continue on *HaAluma* Street.
Vehicle entry and exit will not be possible on these streets while the work is in progress. Please plan accordingly.
*Tuesday, August 18, 2026*
From 07:00 until approximately 14:00, work will focus on *HaKatzir Street*.
During this time, vehicle entry to and exit from HaAluma and HaKatzir Streets will be permitted only with the assistance of traffic directors.
From approximately 14:00 onwards, work will focus on the section between the *two roundabouts on HaDagan Street*.
During this time, vehicle entry to and exit from HaAluma Street will be permitted only with the assistance of traffic directors.
Please plan accordingly.
*Public Transportation on Tuesday*
The HaKatzir stop and the HaDagan stop (between the two roundabouts) are suspended.
Alternative route: Via HaOmer Street, returning to HaZorim, and from there to the first roundabout on HaDagan.
*Wednesday and Thursday, August 19–20*
Work will focus on *HaZor'im* and *HaOmer* streets.
Starting at 07:00, work will proceed from the *HaOmer*/*HaZor'im* intersection toward the kindergarten area.
Upon completion of this phase—likely starting Thursday morning—work will continue along the northern section of *HaZor'im* Street, moving to *HaOmer* Street and continuing up to the *HaOmer*/*HaKatzir* intersection.
Vehicle access (entry and exit) within the work zone will be restricted while work is in progress, depending on the work's advancement.
Please follow the instructions of on-site traffic controllers and plan accordingly.
*Public Transportation – Wednesday and Thursday*
Suspended stops: *HaZor'im* Street, *HaOmer* Street.
Alternative route: From *HaZor'im*/*HaOmer*, via *HaOmer* Street to *HaKatzir* Street, then continuing along the regular route.
*Sunday of the following week – August 23, 2026*
Work will focus on HaOmer Street; a separate notice will be issued.
👈*A quick reminder*: During working hours, vehicle entry and exit within the work zone will not be possible,
in order to ensure continuous, rapid progress and complete the work as soon as possible.
Please plan accordingly and park your vehicles on nearby streets—
vehicle entry or exit during work hours will not be permitted, except in cases of emergency.
👈Pedestrian access will be maintained throughout the duration of the work.
Please follow the instructions of the on-site traffic controllers and drive slowly and carefully.
Thank you for your understanding.
August 13, 2026 481