• Location: Wickliffe, Kentucky
• Capacity: 3.8 MW confirmed substation capacity
‣ 2 MW fully energized
‣ Additional 1.8 MW expansion capacity confirmed
‣ Expansion just requires additional transformer and container infrastructure
• Power price: 5.2¢/kWh historic effective rate (accounting for DR) ⚡️
• Utility: Kentucky Utilities TODP commercial account
‣ All T&D charges bundled
‣ No separate wheeling or transmission charges
• Demand Response: $75,000/MW/year
‣ Only ~ 25 hours curtailed in the latest contract term
• Deal structure: Entity acquisition
‣ Preserves the KU account, active DR contract, permits, and operating setup
‣ Includes land title and all existing infrastructure
• Infrastructure:
‣ New Maddox 2,500 kVA transformer
‣ 1x 1 MW custom-built air-cooled container
‣ 2x 0.5 MW Giga air-cooled containers
‣ 500+ ASIC fleet
‣ 2.5 Gbps symmetrical fiber
• 0.25 acres of owned land
• 5 years of operating history
• Located within a Qualified Opportunity Zone (QOZ)
PRICE: $790k