PMP Preparation (PrePMP) by Dr.Behrangi(PMP-PMI)®## Scenario A company is implementing a cloud-based procurement system across three regional offices. The project is in the execution phase, and testing has revealed intermittent integration failures with the finance platform in one region. At the same time…
B. Update the risk register with the identified threats and assess probability and impact.

That is the first step because multiple new threats have emerged, but their severity and urgency still need structured assessment before taking action. Escalation, supplier replacement, or scope reduction may become appropriate later, but not before the risks are formally identified, analyzed, and prioritized.