📝 ሶስት ተቋራጮች ጨረታ አቀረቡ | Three contractors submitted bids.
፩. ተቋራጭ ‘A’ | Contractor ‘A’
* Technical - 26 %
* Financial- 95 million birr
፪. ተቋራጭ ‘B’ | Contractor ‘B’
* Technical - 29 %
* Financial- 100 million birr
፫. ተቋራጭ ‘C’ | Contractor ‘C’
* Technical - 24 %
* Financial- 90 Milion Birr
💪 Technical evaluation is taken 30% | ቴክኒካል ከ 30% ነው የ ሚገመገመው
♦️ በዚህ መሰረት
1. Determine the financial score of each bidder. የእያንዳንዱን ተጫራች የፋይናሻል ውጤት ይወስኑ።
2. Compute the final weighted score.
የመጨረሻውን የክብደት ነጥብ ያሰሉ።
3. Rank the contractors. የኮንትራክተሮችን ደረጃ ይስጡ።
4. Recommend the winning bidder. አሸናፊውን ተጫራች ይምረጡ።